WSJF

TTool · WSJF

By , Editor · · What’s Next

The backlog is prioritised by size. Big initiatives go first because they feel important. Meanwhile, small high-value work waits in the queue, losing value every day.

Weighted Shortest Job First (WSJF) is SAFe's economic sequencing method. You divide Cost of Delay — combining user value, time criticality, and risk reduction — by job size. Higher scores go first. The maths favours small, high-value items.

A division equation laid out as a formula: a Cost of Delay column (value, time criticality, risk reduction) summing to 60, divided by duration of 3 team-weeks, equalling a WSJF score of 20, above three ranked outcome bars reading runs first / second / third with scores 20, 12 and 7.
Method visual — WSJF